This paper addresses a scheduling problem with unrelated parallel machines, sequence dependent setups and due dates. The problem is based on a real case and the objective is to minimise the sum of the makespan and the weighted delays. A mixed integer linear programming model is proposed and since the model considers realistic constraints, a metaheuristic based on GRASP is used as a solution method. Several versions of the metaheuristic are tested and multiple instances of the problem with different configurations are generated to test the solution quality and the computational performance.
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.