This article presents strategies for teaching scheduling methods such as takt-time, flowlines, and point-to-point precedence relations (PTPPRs) using building information modeling (BIM) models in the Last Planner System. This article is the extended version of the article entitled "Teaching Takt-Time, Flowline and Point-to-point Precedence Relations: A Peruvian Case Study," which has been published in Procedia Engineering (Vol. 196, 2017, pages 666-673). A case study is conducted in final year students of civil engineering at the Pontifical Catholic University of Peru. The mock-up project is an educational building that has high repetitive processes in the structural works phase. First, traditional tools such as Excel spreadsheets and 2D drawings were used to teach production system design with takt-time, flowlines, and PTPPR. Second, 3D and 4D models with Revit 2016 and Navisworks 2016 were used to integrate the previous schedules with a BIM model and to identify its strengths and weaknesses. Finally, Vico Office was used for the automation of schedules and comparison of the methods in 4D and 5D. This article describes the lectures, workshops, and simulations employed, as well as the feedback from students and researchers. The success of the teaching strategy is reflected in the survey responses from students and the final perceptions of the construction management tools presented.
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.