A time-cost trade-off model by incorporating fuzzy earned value management: A statistical based approach

Abstract: Time-cost trade-off problems (TCT) are well-known in project management contents. This approach normally applied for scheduling of a project especially where the project should be completed under pre-determined deadline. This paper aims to extend time-cost trade-off (TCT) problems in order to provide a well-organized mechanism for both scheduling and rescheduling processes of a project. The proposed mechanism includes project scheduling which concerns with the TCT problem, monitoring of project performance dur… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1
1
1

Citation Types

0
8
0

Year Published

2019
2019
2023
2023

Publication Types

Select...
7
2

Relationship

0
9

Authors

Journals

citations
Cited by 13 publications
(8 citation statements)
references
References 36 publications
0
8
0
Order By: Relevance
“…The described challenges have led researchers to develop alternative methods that build on the Earned Value Method, but attempt to more reliably predict the total cost and completion date of projects. Examples of such methods include estimating cost and time by dividing or packing construction work [31], using statistical methods [32,33], applying fuzzy Earned Value Management [34][35][36] or hybrid artificial intelligence [37].…”
Section: Earned Value Methodsmentioning
confidence: 99%
“…The described challenges have led researchers to develop alternative methods that build on the Earned Value Method, but attempt to more reliably predict the total cost and completion date of projects. Examples of such methods include estimating cost and time by dividing or packing construction work [31], using statistical methods [32,33], applying fuzzy Earned Value Management [34][35][36] or hybrid artificial intelligence [37].…”
Section: Earned Value Methodsmentioning
confidence: 99%
“…In Iran, Salari et al (2015) conducted research to develop TCT problems to reach an ordered structure for the organization and reorganization of a project processes. This control mechanism was detected as a help to project managers to utilize a thorough model for scheduling, controlling and rescheduling a project through a life cycle.…”
Section: Fuzzy Logic and Megaprojectsmentioning
confidence: 99%
“…In Iran, Salari et al . (2015) conducted research to develop TCT problems to reach an ordered structure for the organization and reorganization of a project processes.…”
Section: Solution Approachesmentioning
confidence: 99%
“…Orm and Jeunet [8] provided an overview of time-cost-quality trade-off (TCQT) studies with a particular focus on how quality is assessed in previous studies. Salari et al [9] considered the application of statistical modeling and earned value management (EVM) for the TCT problem in a fuzzy environment. He et al [10] developed variable neighborhood search and tabu search algorithms in a discrete TCT problem minimizing the maximum difference between contractor input and output cash flows.…”
Section: Introduction and Literature Reviewmentioning
confidence: 99%