Abstract:Schedule delays commonly appear in construction projects and result in delay claim progressively. Several studies have proposed various schedule delay analysis methodologies; however, most of the studies focus on the analysis of surface data (as-planned and as-built schedules), few of them on evaluating the effects of root causes, such as the problem of lost productivity. Lost productivity, one essential delay cause, is usually experienced by a contractor while accomplishing its works less than planned rate of… Show more
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.