Cost and Time Analysis Using Earned Value Method on the Construction of the National Kediri Airport Access Road Phase 1 Kediri - Nganjuk
Ichsan Yanuansyah Pramadha,
Hanie Teki Tjendani,
Budi Witjaksana
Abstract:Project completion delays have adverse consequences on a contractor's credibility and result in additional penalty costs, reducing potential profits. To mitigate these issues and optimize project outcomes, refining activity schedules and budgets is crucial. The Earned Value Method proves effective in monitoring and controlling project activities. In the case of the Kediri airport access road construction project, weeks 1 to 6 revealed a negative Cost Variance (CV), indicating higher-than-planned costs, while w… Show more
Set email alert for when this publication receives citations?
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.