2018
DOI: 10.3390/su10072469
|View full text |Cite
|
Sign up to set email alerts
|

Detail Engineering Completion Rating Index System (DECRIS) for Optimal Initiation of Construction Works to Improve Contractors’ Schedule-Cost Performance for Offshore Oil and Gas EPC Projects

Abstract: Engineering, Procurement, and Construction (EPC) contractors with lump-sum turnkey contracts have recently been suffering massive profit losses due to re-works and schedule delays in offshore oil and gas EPC megaprojects. The main objective of this research is to develop and implement a detail engineering completion rating index system (DECRIS) to assist EPC contractors to optimize fabrication and construction works schedules while minimizing potential re-work/re-order. This is achieved through adequate detail… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
3
1
1

Citation Types

0
39
0

Year Published

2019
2019
2024
2024

Publication Types

Select...
5
1

Relationship

2
4

Authors

Journals

citations
Cited by 16 publications
(39 citation statements)
references
References 10 publications
0
39
0
Order By: Relevance
“…There are many existing publications dedicated to causes of profit losses and construction delays on international EPC mega projects: Asia [5][6][7][8][9][10][11][12][13][14][15][16], Europe [17,18], Africa [19][20][21][22], Americas [23][24][25], and Australia [26,27]. Among the factors identified, the most common cause of project schedule and cost overrun was found to be poor design development prior to construction [5][6][7][8]12,13,[15][16][17][18][22][23][24]27].…”
Section: Existing Literaturementioning
confidence: 99%
See 1 more Smart Citation
“…There are many existing publications dedicated to causes of profit losses and construction delays on international EPC mega projects: Asia [5][6][7][8][9][10][11][12][13][14][15][16], Europe [17,18], Africa [19][20][21][22], Americas [23][24][25], and Australia [26,27]. Among the factors identified, the most common cause of project schedule and cost overrun was found to be poor design development prior to construction [5][6][7][8]12,13,[15][16][17][18][22][23][24]27].…”
Section: Existing Literaturementioning
confidence: 99%
“…The PDRI's hierarchy consists of sections, categories, and elements. Each element is assessed on a scale of 1 to 5, and a project definition rating is calculated using a scoresheet which is weighted and normalized for each element [8]. The CII recommends that the cutoff score of the PDRI at the end of the FEED stage should be 200, as the performance of a project with a score higher than 200 was historically not satisfactory in terms of cost and schedule.…”
Section: Existing Literaturementioning
confidence: 99%
“…While there exist a multitude of studies modelling construction schedules, research on estimating schedules and predicting the potential delays for O&G project construction related to automated modelling are few. A detailed engineering completion rating index system model was developed and implemented to assist offshore EPC contractors for optimizing fabrication and construction work schedule with minimizing possibility of repetition of works [20,21]. Jo et al [22] developed a methodology of piping construction delay prevention to improve material procurement management and avoid shortage of piping materials and to minimize delays, by using the critical chain project management.…”
Section: Literature Reviewmentioning
confidence: 99%
“…Note, this process of developing an SDRI scoring has precedence within existing literature, though the score has been given many names. The scoring method most similar to the presented SDRI models the project definition rating index (PDRI) by the Construction International Institute (CII) [44] and two papers on the Detail Engineering Completion Rating Index System (DECRIS) [20,21]. These two indexes are typically used by the project owner and EPC contractor to quantify the level of basic and detailed engineering maturity to determine whether the project can move to the next development stage by mapping PDRI scores and DECRIS score to project performances of schedule delay and cost overrun in the EPC execution stage.…”
Section: Ct Doc 1 Docmentioning
confidence: 99%
See 1 more Smart Citation