Abstract:The research results of this paper show that parameters of the catch-up schedule are determined by the dynamics of time-averaged volumes, rates and accelerations of construction jobs only when discrete nature of resources consumed has a weak influence on the rate of project jobs. On the other hand, if the speed of job is determined by the use of nostockable resources, the dynamics of jobs volume demonstrates the weak sensitivity both to the discrete nature of resources and to external stochastic influences. In… Show more
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.