Modeling the Causes and Mitigation Measures for Cost Overruns in Building Construction: The Case of Higher Education Projects

Yasir Alhammadi,
Mohammad S. Al-Mohammad,
Rahimi A. Rahman

Abstract: The formidable need for building projects places greater pressure on stakeholders to deliver these projects on time, within the budget, and with high quality. However, many building projects have experienced extensive cost overruns despite extensive research on their causes and mitigation measures. Thus, the effectiveness of mitigation measures is questionable. This study examines the status of cost overrun in building construction projects and develops a structural equation model to establish the relationship… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2

Citation Types

0
2
0

Year Published

2024
2024
2024
2024

Publication Types

Select...
5

Relationship

0
5

Authors

Journals

citations
Cited by 10 publications
(2 citation statements)
references
References 80 publications
0
2
0
Order By: Relevance
“…This research mainly intends to solve the issue of unreliable or ineffective cost estimations in civil engineering initiatives. Unreliable or not good enough cost estimates in AEC projects are a big problem, as established in [7]. This problem happens due to reasons like wrong data, not enough project planning, unexpected risks, and not enough skills.…”
Section: Problems To Be Solved In This Studymentioning
confidence: 99%
See 1 more Smart Citation
“…This research mainly intends to solve the issue of unreliable or ineffective cost estimations in civil engineering initiatives. Unreliable or not good enough cost estimates in AEC projects are a big problem, as established in [7]. This problem happens due to reasons like wrong data, not enough project planning, unexpected risks, and not enough skills.…”
Section: Problems To Be Solved In This Studymentioning
confidence: 99%
“…When cost estimates are unreliable, the authors in [7] say it can lead to spending more money, delays, and poor project quality. Wrong cost guesses can also complicate resource utilization and lead to conflicts among stakeholders.…”
Section: Problems To Be Solved In This Studymentioning
confidence: 99%