2017
DOI: 10.1016/j.tust.2017.03.002
|View full text |Cite
|
Sign up to set email alerts
|

A case study of TBM performance prediction using a Chinese rock mass classification system – Hydropower Classification (HC) method

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
18
0

Year Published

2017
2017
2022
2022

Publication Types

Select...
8
1

Relationship

0
9

Authors

Journals

citations
Cited by 100 publications
(18 citation statements)
references
References 40 publications
0
18
0
Order By: Relevance
“…The wave velocity of the rock mass can be identified through acoustic test methods such as the single-hole method, cross-hole method, and hammering method [22]. As the acoustic test results are significantly influenced by drilling direction, the cross-hole method was conducted to determine the p-wave velocity of rock mass in the study area and the typical results are given in Figure 6.…”
Section: Geology Investigation Of the Underground Powerhousementioning
confidence: 99%
“…The wave velocity of the rock mass can be identified through acoustic test methods such as the single-hole method, cross-hole method, and hammering method [22]. As the acoustic test results are significantly influenced by drilling direction, the cross-hole method was conducted to determine the p-wave velocity of rock mass in the study area and the typical results are given in Figure 6.…”
Section: Geology Investigation Of the Underground Powerhousementioning
confidence: 99%
“…In this study, the rock mass geomechanical RMR value is converted into Barton's Q value using the basic rock mass quality index BQ value, the empirical conversion formula of the rock mass geomechanical RMR value [37], the Barton rock mass quality Q value given by Barton considering joint orientation, and the rock mass geomechanical RMR value [38]. en, the Barton-modified Q′' value of the rock mass was solved.…”
Section: Acquisition Of Rock Parametersmentioning
confidence: 99%
“…To be simple, detailed evaluation procedures and criterions could be referenced [5,7,[63][64][65][66][67][68]. Besides, all the correction factors of BQ method and the stress reduction factor of Q-system method could be calculated and analyzed by interval-number mathematics.…”
Section: Membership Probability Calculationmentioning
confidence: 99%
“…at is, groundwater condition A w can be determined by groundwater quantity, groundwater pressure, and seepage condition. For the sake of simplicity, some literature [6,64,77] can be referenced for more details. Since most of the burial depth of Laohushan tunnel is 20-60 m, the in situ stress would not be considered here.…”
Section: Selection Of Evaluation Indicesmentioning
confidence: 99%