A multi-agent-based system for two-stage scheduling problem of offshore project

Abstract: Aimed at enhancing the effectiveness and efficiency for offshore project scheduling, the mathematical model of two-stage scheduling is proposed according to the offshore project characteristics discussed in this article, which is used to solve the scheduling problem of large-scale and complex project. Regarding the two-stage scheduling, a system framework with multi-agent technology is presented to facilitate the integration and cooperation of offshore project scheduling. Next, the functional definition and in… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
4
1

Citation Types

0
5
0

Year Published

2018
2018
2022
2022

Publication Types

Select...
7

Relationship

1
6

Authors

Journals

citations
Cited by 8 publications
(5 citation statements)
references
References 35 publications
0
5
0
Order By: Relevance
“…The research is a good example of how large-scale decision problems require specialized multi-layered decision logics, which in this case is further improved upon through allowing parallel processing of the computations in the final decision layer. Han et al 4 consider the problem of offshore project scheduling and propose a two-stage multi-agent approach to address this. To facilitate the solution, two different kinds of algorithms have been designed and implemented.…”
Section: Intelligent Manufacturing/production Systems: Modeling Algorithms and Optimizationmentioning
confidence: 99%
“…The research is a good example of how large-scale decision problems require specialized multi-layered decision logics, which in this case is further improved upon through allowing parallel processing of the computations in the final decision layer. Han et al 4 consider the problem of offshore project scheduling and propose a two-stage multi-agent approach to address this. To facilitate the solution, two different kinds of algorithms have been designed and implemented.…”
Section: Intelligent Manufacturing/production Systems: Modeling Algorithms and Optimizationmentioning
confidence: 99%
“…As a typical large-scale engineering project, shipbuilding project has the characteristics of complex product structure, multiple manufacturing links, long production cycle, tight delivery, jobbing work, As a typical large-scale engineering project, shipbuilding project has the characteristics of complex product structure, multiple manufacturing links, long production cycle, tight delivery, jobbing work, multi-project parallelism, frequent engineering alterations, and so on [3]. The shipbuilding process is extremely complicated.…”
Section: Introductionmentioning
confidence: 99%
“…Aiming at the problem, some related studies have been carried out. Literature has shown tendency about multitask scheduling of AGV systems and FMS; minimizing makespan and several other criteria are introduced to meet the demands of actual-practice scheduling [31][32][33]. Udhayakumar and Kumanan addressed tasks scheduling of AGVs in a flexible manufacturing environment using nontraditional optimization algorithms and made an attempt to find the near-optimum schedule for two AGVs based on the balanced workload and the minimum traveling time for maximum utilization [34].…”
Section: Introductionmentioning
confidence: 99%