Accepted: 16 February 2016 A comprehensive case study of manufacturing scheduling solutions development is given. It includes highly generalized scheduling problem as well as a few scheduling modes, methods and problem models. The considered problem combines flexible job shop structure, lot streaming with variable sublots, transport times, setup times, and machine calendars. Tabu search metaheuristic and constraint programming methods have been used for the off-line scheduling. Two dynamic scheduling methods have also been implemented, i.e., dispatching rules for the completely reactive scheduling and a multi-agent system for the predictivereactive scheduling. In these implementations three distinct models of the problem have been used, based on: graph representation, optimal constraint satisfaction, and Petri net formalism. Each of these solutions has been verified in computational experiments. The results are compared and some findings about advantages, disadvantages, and suggestions on using the solutions are formulated.