An Improved Integrated Scheduling Algorithm with Process Sequence Time‐Selective Strategy

Abstract: The integrated scheduling algorithm of process sequence time-selective strategy (ISAOPSTSS) is an advanced algorithm in the field of integrated scheduling. The proposed algorithm points out the shortcomings of the process sequence time-selective strategy. Generally, there are too many “trial scheduling” times. The authors propose that there is no need to make “trial scheduling” at every “quasi-scheduling time point.” In fact, the process scheduling scheme can be obtained by trial scheduling on some “quasi-sche… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1

Citation Types

0
2
0

Year Published

2022
2022
2024
2024

Publication Types

Select...
3
1

Relationship

0
4

Authors

Journals

citations
Cited by 4 publications
(2 citation statements)
references
References 24 publications
0
2
0
Order By: Relevance
“…Without losing generality, 100 product PTs were randomly generated. The following parameters were randomly generated: the number of processes is [20,50], the number of immediate predecessor processes of each non-leaf node is [1,10], the number of machining equipment is [3,10], and the machining time of a process is [1,20]. The software used on the experimental platform was Windows 7, 64-bit, GCC5.0, and the hardware of the experimental platform was an Intel Core i5-3470S processor with 4 GB of memory.…”
Section: Experimental Data and Environmentmentioning
confidence: 99%
See 1 more Smart Citation
“…Without losing generality, 100 product PTs were randomly generated. The following parameters were randomly generated: the number of processes is [20,50], the number of immediate predecessor processes of each non-leaf node is [1,10], the number of machining equipment is [3,10], and the machining time of a process is [1,20]. The software used on the experimental platform was Windows 7, 64-bit, GCC5.0, and the hardware of the experimental platform was an Intel Core i5-3470S processor with 4 GB of memory.…”
Section: Experimental Data and Environmentmentioning
confidence: 99%
“…The research has gone through a process from focusing on the path length (vertical) of the product process tree affecting the scheduling results to focusing on the SLP (horizontal) of the product process tree affecting the parallel scheduling results. Representative algorithms include the dynamic critical path method [17], time-selective adjustment method [18][19][20], and reverse order scheduling method [21], etc.…”
Section: Introductionmentioning
confidence: 99%