2020
DOI: 10.37265/japiv.v10i1.24
|View full text |Cite
|
Sign up to set email alerts
|

Analysis of Cost Overruns in Saudi Arabia Construction Projects: A University Case Study

Abstract: Public projects in Saudi Arabia have been experiencing low construction project performance for the past decade. Studies have identified the low-bid delivery method as an important factor in causing such delays. In addition, low bids for contracts have not reflected the actual project cost. A case study was conducted at a university campus in northern Saudi Arabia in which the actual project costs for four projects were examined. The study found that all four projects’ costs were higher than the original bid. … Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
8
0

Year Published

2020
2020
2024
2024

Publication Types

Select...
5
1

Relationship

0
6

Authors

Journals

citations
Cited by 6 publications
(8 citation statements)
references
References 32 publications
0
8
0
Order By: Relevance
“…Contracting with the lowest bidder was also found to be one of the top contributors to schedule delays in public construction projects in Saudi Arabia. Alzara, et al (2018) analysed cost overruns in the construction of a higher education institute in Saudi Arabia and found that bids submitted by construction companies who eventually succeeded in getting the contract, were much lower than the market project costs. This was remediated through variation and change orders that led to cost overruns.…”
Section: Contributors To Poor Project Deliverymentioning
confidence: 99%
See 3 more Smart Citations
“…Contracting with the lowest bidder was also found to be one of the top contributors to schedule delays in public construction projects in Saudi Arabia. Alzara, et al (2018) analysed cost overruns in the construction of a higher education institute in Saudi Arabia and found that bids submitted by construction companies who eventually succeeded in getting the contract, were much lower than the market project costs. This was remediated through variation and change orders that led to cost overruns.…”
Section: Contributors To Poor Project Deliverymentioning
confidence: 99%
“…Therefore, the final product could differ widely from what had been initially planned. The inefficient and ineffective project implementation is a result of traditional regulations as well as poor management practices; either those of the owner's organization, the pre-construction team or the construction team, as referred to by Gopang, Imran and Nagapan (2020), Mitra and Wee Kwan Tan (2012), Simushi (2017), Alofi, Kashiwagi and Kashiwagi (2016) and Alzara, et al (2018). The project manager as a focal point is appointed after the contract awarding.…”
Section: Project Initiationmentioning
confidence: 99%
See 2 more Smart Citations
“…Findings indicated that out of the 34 different items used to measure causes of cost overrun, the most important factors included: awarding of tender, or bids to the lowest bidder, change in design of the project by the owner, or consultant, inadequate project planning, lengthy periods between project design and actual implementation, and delay in payments. Alzara, Kashiwagi, and Al-Tassan (2016) expounded on the relationship between change order and cost overrun among the lowest bidding contractors. Firstly, the author explains the problem with the tendering system of KSA, where many bids are awarded to the contractors who present the lowest cost estimate for completing the project.…”
Section: Cost Overrun In Causes In Construction Projectmentioning
confidence: 99%