Abstract:In order to analyze some of the reasons for the delays in the implementation and the beginning of the operation of transmission system projects in Brazil, this study considers the deadlines and definitions of the regulations of the MMA Ordinance No. 421/2011, Interministerial Ordinance No. 60/2015, MS/SVS Ordinance 01/2014, IPHAN RI 001/2015 and FCP RI 01/2018, applicable in the environmental licensing of energy transmission enterprises. The analysis focused on the simplified federal environmental licensing, d… Show more
Set email alert for when this publication receives citations?
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.