Commissioning and Operational Experience from FRIB Target and Fragment Pre-separator Superconducting Magnet Quench Management System

Nusair Hasan,
Venkatarao Ganni,
Peter Knudsen
et al.
Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1

Citation Types

0
2
0

Year Published

2024
2024
2024
2024

Publication Types

Select...
3

Relationship

0
3

Authors

Journals

citations
Cited by 3 publications
(2 citation statements)
references
References 5 publications
0
2
0
Order By: Relevance
“…In addition to upgrades of the aging equipment and legacy SC magnets (discussed in section 6.2), adoption of a quench recovery system for future expansion of the facility is also being considered. The newly commissioned SC magnets for the FRIB target and pre-separator segment (designed for higher operating pressure) incorporates such a system [29,30], which has shown excellent performance so far [31].…”
Section: Cryogenicsmentioning
confidence: 99%
“…In addition to upgrades of the aging equipment and legacy SC magnets (discussed in section 6.2), adoption of a quench recovery system for future expansion of the facility is also being considered. The newly commissioned SC magnets for the FRIB target and pre-separator segment (designed for higher operating pressure) incorporates such a system [29,30], which has shown excellent performance so far [31].…”
Section: Cryogenicsmentioning
confidence: 99%
“…The superconducting magnets and their associated cryogenic distribution (see ES Distribution, Figure 1) for this segment were designed and commissioned recently (CY2020-22) [7] as part of the FRIB project. A unique superconducting magnet quench recovery system as well as a controlled cool-down system were also designed, commissioned, and integrated as part of this cryogenic distribution system [8].…”
Section: Present Cryogenic Loads and Configurationmentioning