Design Considerations for the Implementation of Tailings Based Wetcrete at Harmony's Target Mine

Abstract: The Target Mine orebody is situated approximately 2400 m below surface and is accessed via a vertical shaft and decline system, totalling approximately 6000 m in length. This requires that all modes of transport be optimised. As a result of the heavy burden on the mine's logistical transport system, the mine was unable to deliver sufficient quantities of wetcrete material to the underground batching plant. This resulted in a relatively large backlog of wetcrete work building up over a number of years. The mine… Show more