In Critical Path Method (CPM), the project managers usually use three quantities; earliest start, latest start and job float for project networking problems. However, interval parameters are used for project scheduling problems dealing with the uncertainties. In this paper, we suggest a new approach for computing the interval time duration of a project networking problem without transforming to crisp equivalent forms. First the interval parameters are represented in their midpoint width form. A new type of arithmetic operations and ranking are applied on the midpoint width form of interval numbers, earliest start, latest start, earliest finish, latest finish and float time are calculated. Interval critical path is identified and the project completion tine is arrived. Numerical description is supplied to describe the method proposed in depth and the results obtained are compared with the existing methods.