Discussion of Papers 6831 and 6826. Clyde Tunnel: Design, Construction and Tunnel Services. Constructional Problems.

Abstract: ) said that the Authors and their colleagues were to be congratulated on the successful completion of this notable work in the face of very difficult conditions. 155. The Authors of the first Paper said in 5 17 that because of hazards to, and from shipping it was not possible to sink boreholes within the width of the river and it was realized that much uncertainty must exist as to the nature of the ground there until the first pilot tunnel had been driven. As it happened there was a good cover of boulder clay … Show more