Integration of FMEA and Bayesian network methods for risk assessment of components delay in ferry ship construction
Zulfaidah Ariany,
Trika Pitana,
Iwan Vanany
Abstract:Construction of new ships in Indonesia. In this case study, the construction of a 600 DWT Ro-Ro ferry. The 600 DWT Shipbuilding Project involves various risks that may affect the schedule and results. A risk assessment involving the quality control team, project lead, and production management is carried out to identify and quantify the level of risk and its consequences.
The results of this assessment assist in understanding and managing project risk, stress the importance of communication and coordinat… Show more