Lessons Learned From the Qualification Program and J-laying Campaign of 12-inch Steel Catenary Risers for the P55 Deepwater Project

Abstract: This paper reports the Lessons Learned from an innovative linepipe solution that was successfully implemented on P55 Deepwater Project. The P55 field is located offshore Brazil, in the northern area of Campos Basin, in a water depth ranging from 1500m to 1900m. The scope of work consisted in engineering, procuring, fabricating and installing 16 rigid Steel Catenary Risers (SCRs), which are the first of their kind in this area. The corresponding 12-inch SCR qualification results are presented in the perspective… Show more