Construction practitioners often experience unexpected results of their scheduling-related decisions. This is mainly due to lack of understanding of the dynamic nature of construction system. However, very little attention has been given to its significant importance and few empirical studies have been undertaken on this issue. This paper, therefore, analyzes the effect of aggressive scheduling, overtime, resource adding, and schedule slippage on construction performance, focusing on workers' reactions to those scheduling decisions. Survey data from 102 construction practitioners in 38 construction sites are used for the analysis. The results indicate that efforts to increase work rate by working overtime, resource adding, and aggressive scheduling can be offset due to losses in productivity and quality. Based on the research findings, practical guidelines are then discussed to help site managers to effectively deal with the dynamics of scheduling and improve construction performance.