Optimal generation maintenance scheduling considering financial return and unexpected failure of distributed generation

Abstract: Generation maintenance scheduling (GMS) is an important factor that can improve the reliability of power systems and decrease revenue achieved by generation companies (GenCos). Several GMS models, therefore, are based on these two crucial values. Nonetheless, there is no GMS problem that simultaneously considers unexpected failure of distributed generator (DG), financial return of GenCo, and reserve of system. This paper proposes the GMS model based on a global criterion approach to compromise functions that m… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
2
0

Year Published

2023
2023
2023
2023

Publication Types

Select...
2
1
1

Relationship

1
3

Authors

Journals

citations
Cited by 4 publications
(6 citation statements)
references
References 46 publications
0
2
0
Order By: Relevance
“…The mp b,j and D b,t are extracted from [25] and [20,38], respectively. To find the results, there is an assumption that the load demand and electricity price are certain [20,22,23,25,34], while the power loss is not considered. The T is divided into 52 weeks, based on yearly maintenance scheduling, whereas the H is 24 × 7 = 168 h. The δ is assumed to be 0.1 (10%) [23].…”
Section: Numerical Resultsmentioning
confidence: 99%
See 2 more Smart Citations
“…The mp b,j and D b,t are extracted from [25] and [20,38], respectively. To find the results, there is an assumption that the load demand and electricity price are certain [20,22,23,25,34], while the power loss is not considered. The T is divided into 52 weeks, based on yearly maintenance scheduling, whereas the H is 24 × 7 = 168 h. The δ is assumed to be 0.1 (10%) [23].…”
Section: Numerical Resultsmentioning
confidence: 99%
“…To efficiently obtain the results, as shown in Equations ( 12)-( 14), the natural logarithm is used to linearize the model. The linearized Z is represented by PnF', which should also have a low value, similar to that for Z [22,34].…”
Section: Gms Indicesmentioning
confidence: 99%
See 1 more Smart Citation
“…In addition, the reserved energy should be above a certain level when some of the generation units are undergoing maintenance, so that the risks of large-scale load loss caused by a reserved energy shortage can be avoided. Thus, the maintenance schedules are required to be properly planned [4][5][6][7]. The ISO manages the planning process of the maintenance considering the costs of maintenance actions for the generation units and the power system reliability.…”
Section: Introductionmentioning
confidence: 99%
“…The study also addresses the power generating cost by reducing the team visit to each PP as high power generating PPs cost is high and it affects the other PP module's expected regular service output in the long run (Cai et al, 2020). This problem is addressed by developing an algebraic framework for connecting different cities in the western region to a single loop having a minimum length between maintenance centers and setting up an appropriate number of teams for reliable and stable power supplies (Prukpanit et al 2021).…”
Section: Research Problemmentioning
confidence: 99%