Polynomial algorithms for some scheduling problems with one nonrenewable resource

Abstract: This paper deals with the Extended Resource Constrained Project Scheduling Problem (ERCPSP) which is defined by events, nonrenewable resources and precedence constraints between pairs of events. The availability of a resource is depleted and replenished at the occurrence times of a set of events. The decision problem of ERCPSP consists of determining whether an instance has a feasible schedule or not. When there is only one nonrenewable resource, this problem is equivalent to find a feasible schedule that mini… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...

Citation Types

0
0
0

Publication Types

Select...

Relationship

0
0

Authors

Journals

citations
Cited by 0 publications
references
References 28 publications
0
0
0
Order By: Relevance

No citations

Set email alert for when this publication receives citations?