pp collider construction scenario

Abstract: In order to bring the Fermilab proton-proton colliding-beam facility into operation at the earliest possible time, dose coordination between the variouc aspects of the construction is essential. We present a possible scenario for how the installation might proceed, and point out some important consequences for planning in the immediate future. Table I represents our attempt to fit together the various phases of construction in an optimistic yet realistic fashion. We have not tried to integrate the pp or ep col… Show more