2003
DOI: 10.1016/s0377-2217(02)00768-3
|View full text |Cite
|
Sign up to set email alerts
|

Resource-constrained project scheduling: A critical activity reordering heuristic

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1
1
1

Citation Types

0
41
0

Year Published

2005
2005
2017
2017

Publication Types

Select...
6
2
1

Relationship

0
9

Authors

Journals

citations
Cited by 94 publications
(41 citation statements)
references
References 21 publications
0
41
0
Order By: Relevance
“…Solution representation: since delays in sections 4.1 and 4.2 are done according to the order in which activities appear in the PL, we employ the topological order (TO) representation first proposed by Valls et al (2003Valls et al ( , 2004, and used for the RCPSP by Debels et al (2006). The TO representation ensures a precedence feasible ordering of activities and is updated based on actual finish times after the improvement methods discussed in sections 4.2.2 and 4.2.3 have been applied.…”
Section: Metaheuristicsmentioning
confidence: 99%
“…Solution representation: since delays in sections 4.1 and 4.2 are done according to the order in which activities appear in the PL, we employ the topological order (TO) representation first proposed by Valls et al (2003Valls et al ( , 2004, and used for the RCPSP by Debels et al (2006). The TO representation ensures a precedence feasible ordering of activities and is updated based on actual finish times after the improvement methods discussed in sections 4.2.2 and 4.2.3 have been applied.…”
Section: Metaheuristicsmentioning
confidence: 99%
“…• Representation of a schedule: Based on the remarks by Debels et al (2006) who have illustrated that a random key representation is very effective thanks to the use of the topological ordering notation (Valls et al, 2003), this notation has been adapted to the dual population heuristic, as follows: the random key elements are equal to the activity finishing times for a left-justified schedule, and equal to the starting times for a right-justified schedule.…”
Section: Rcpsp Scheduling Stepmentioning
confidence: 99%
“…This representation consists of the starting times of the sub-activities with a positive duration in increasing order followed by set of remaining activity modes that are not part of the feasible schedule (i.e. the sub-activities with a duration of zero) and is an extension of the topological order representation of Valls et al (2003Valls et al ( , 2004. Since a feasible project schedule can be uniquely defined by its activity starting times, such an AL can always be constructed.…”
Section: Rcpsp Scheduling Stepmentioning
confidence: 99%
“…Usually, generating a single solution by means of the proposed heuristics requires less than 0.1 s for large problem instances with 600 tests and 25 variants of experimental vehicles. Thus, it is advisable to make use of a so called multi-pass heuristic (Valls et al 2001), where the priority-rule method is applied repeatedly, each time using different priority values .i/. However, since the number of adequate priority-rules is limited, we make use of compound priority rules and values.…”
Section: Multi-start Proceduresmentioning
confidence: 99%