Reworks causes and related costs in construction: case of Parand mass housing project in Iran

Abstract: Purpose The purpose of this paper is to identify the main reworks and their causes in a case study of the ongoing mass housing project in Iran. Using the real data captured from the project, the most important causes for reworks have been computed and prioritized. Design/methodology/approach More than 900 non-conformance forms filled in the construction site have been used to categorize reworks. Then, the frequency and cost of each rework group in the project have been estimated. Finally, using these data, t… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1

Citation Types

0
9
0

Year Published

2021
2021
2024
2024

Publication Types

Select...
4
2

Relationship

0
6

Authors

Journals

citations
Cited by 19 publications
(9 citation statements)
references
References 24 publications
0
9
0
Order By: Relevance
“…Rework on buildings (Oke & Ugoje, 2013;Aiyetan, 2014;Jarkas, 2015;Ade-Ojo et al, 2016;Adomah, 2016;Yap et al, 2017;Eze & Idiake, 2018a, 2018bLiu et al, 2018) Factors influencing rework (Oyewobi & Ogunsemi, 2010;Meshksar, 2012;Simpeh, 2012;Zaiter, 2014;Adomah, 2016;Love et al, 2016;Ajayi, 2017;Enshassi et al, 2017) Client-related rework Jarkas, 2015;Ade-Ojo et al, 2016;Liu et al, 2018) Building defects and rework (Sommerville, 2007;Bakri & Mydin, 2013;Taggart et al, 2014) Rework cost (direct and indirect) ( Oyewobi et al, 2011;Meshksar, 2012;Oke & Ugoje, 2013;Aiyetan, 2014;Zaiter, 2014;Love et al, 2016;Eze & Idiake, 2018a;Liu et al, 2018;Balouchi et al, 2019)…”
Section: Rework Variables Referencesmentioning
confidence: 99%
See 4 more Smart Citations
“…Rework on buildings (Oke & Ugoje, 2013;Aiyetan, 2014;Jarkas, 2015;Ade-Ojo et al, 2016;Adomah, 2016;Yap et al, 2017;Eze & Idiake, 2018a, 2018bLiu et al, 2018) Factors influencing rework (Oyewobi & Ogunsemi, 2010;Meshksar, 2012;Simpeh, 2012;Zaiter, 2014;Adomah, 2016;Love et al, 2016;Ajayi, 2017;Enshassi et al, 2017) Client-related rework Jarkas, 2015;Ade-Ojo et al, 2016;Liu et al, 2018) Building defects and rework (Sommerville, 2007;Bakri & Mydin, 2013;Taggart et al, 2014) Rework cost (direct and indirect) ( Oyewobi et al, 2011;Meshksar, 2012;Oke & Ugoje, 2013;Aiyetan, 2014;Zaiter, 2014;Love et al, 2016;Eze & Idiake, 2018a;Liu et al, 2018;Balouchi et al, 2019)…”
Section: Rework Variables Referencesmentioning
confidence: 99%
“…Direct rework cost can be 5% of the construction cost and it could be as high as 20% (Ade-Ojo et al, 2016;Balouchi et al, 2019). In most construction work, it could range from 3% -10% (Zaiter, 2014).…”
Section: Rework Costmentioning
confidence: 99%
See 3 more Smart Citations