2019
DOI: 10.3390/en12101956
|View full text |Cite
|
Sign up to set email alerts
|

Using Text Mining to Estimate Schedule Delay Risk of 13 Offshore Oil and Gas EPC Case Studies During the Bidding Process

Abstract: Korean offshore oil and gas (O&G) mega project contractors have recently suffered massive deficits due to the challenges and risks inherent to the offshore engineering, procurement, and construction (EPC) of megaprojects. This has resulted in frequent prolonged projects, schedule delay, and consequently significant cost overruns. Existing literature has identified one of the major causes of project delays to be the lack of adequate tools or techniques to diagnose the appropriateness and sufficiency of the … Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
2
1
1
1

Citation Types

0
6
0

Year Published

2020
2020
2024
2024

Publication Types

Select...
9
1

Relationship

0
10

Authors

Journals

citations
Cited by 20 publications
(8 citation statements)
references
References 38 publications
0
6
0
Order By: Relevance
“…A huge amount of data contains vast amounts of potentially valuable information, which can be used to develop the economy and society. However, obtaining useful information from such diverse and heterogeneous samples of data has become a key issue in knowledge management research [9]. Risk data is often recorded and stored as unstructured data.…”
Section: Introductionmentioning
confidence: 99%
“…A huge amount of data contains vast amounts of potentially valuable information, which can be used to develop the economy and society. However, obtaining useful information from such diverse and heterogeneous samples of data has become a key issue in knowledge management research [9]. Risk data is often recorded and stored as unstructured data.…”
Section: Introductionmentioning
confidence: 99%
“…As different types of documents are generated during the life cycle of construction project, TM techniques have a wide range of applications in AEC domains. In addition to the above areas, TM techniques have also been used in defect analysis [ 118 , 119 ], material management [ 120 ], workforce planning [ 121 ], facility management [ 87 , 122 , 123 ], complaints management [ 124 ], contract management [ 113 , 117 ], field inspection [ 125 ], product search [ 126 , 127 ], post-project reviews [ 128 , 129 , 130 , 131 ], cost prediction [ 132 ], quality management [ 68 ], job advertisements [ 133 , 134 ], legal decision support [ 135 ], building renovation [ 136 ], feasibility study [ 137 ], patent analysis [ 138 ], schedule delay [ 139 ], and incident duration prediction [ 140 ].…”
Section: Application Areas Of Tmmentioning
confidence: 99%
“…In other applications of text mining, the risk calculation is usually a separate exercise. For example, Lee and Yi (2017) quantified risk as a factor of the project bid cost while Son and Lee (2019) defined risk as a factor of project delay. Text mining has also been used to identify risk events from accident reports (Sarkar et al., 2016).…”
Section: Related Workmentioning
confidence: 99%