One of the main problems when constructing a metro line using a tunnel boring machine (TBM) is the coordination of the construction of the tunnel with the excavation of the stations that it will intersect. The drilling speed of the tunnel varies from the predicted one, it being possible to reach the stations before their complete excavation. This paper presents a solution to this problem, one which has been implemented in the Riyadh Metro L5. This solution allows the construction of the tunnel and the later excavation of the station, while maintaining the operation of the TBM and the tunnel lining.
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.