As an integral part of Exxon's Santa Ynez Unit (SYU) Expansion Project, the Harmony and Heritage platform jackets were loaded out from a fabrication yard in South Korea, transported across the Pacific Ocean, and installed offshore California in water depths of 1200 feet and 1075 feet, respectively (Figure 1). Overall this was a 9-1/2 month effort, beginning with the Harmony jacket load-out in April, 1989 and ending with the Heritage jacket post-installation inspection in February 1990. INTRODUCTION The loadout, transportation, and installation of the Harmony and Heritage jackets were nearly identical for each jacket. Consequently, this paper is structured to present the Harmony jacket, with reference to the Heritage jacket where procedures differed. A timetable of events for each jacket is provided in Figure 2. LOADOUT AND TIEDOWN After fabrication, each jacket was loaded onto an 853 foot long by 206 foot wide by 49 foot deep barge for separate transportation across the Pacific Ocean. This barge, which is the largest launch barge ever built, was capable of safely transporting and launching the Harmony and Heritage jackets. The Harmony jacket was the first to be loaded out. In preparation, bollards and winches were added to the barge to accommodate the loadout mooring arrangement. Further, considerable dredging and excavation was performed to accommodate the 32 foot maximum draft of the barge during loadout. The barge mooring system included six bow anchor lines attached to anchors and four lines at the stern attached to onshore bollards (Figure 3). For the Heritage loadout, only four bow lines were used due to the proximity of the adjacent quay wall. These four lines were tied back directly to the quay wall. The loadout plan was based on the use of the launch barge's 6000 ton jacking system. Once the mooring system was secured and proof-tested, a wire rope link system was installed to connect the barge hydraulic jacking units to pulling lugs on the jacket. In addition to the barge jacks, breakout was assisted by the use of auxiliary jacks mounted on the skidway. Breakout of the jackets required a pulling/pushing force of approximately 6500 tons for Harmony and 5000 tons for Heritage. In both cases this represented a 15% coefficient of static friction between the jacket launch timbers and the land-based skidways. After breakout, jacking forces steadily declined and stabilized at approximately 3300 tons for Harmony and 2000 tons for Heritage, indicating respectively a 7% and 6% coefficient of friction for the remainder of the loadout. Jacket weight compensation and tidal ballasting of the barge were completed using the barge's main ballast system. An independent tidal ballast system was installed for use in the event of failure of the barge system. During the jacket loadout, ballast operations were properly controlled to keep the barge and jacket positions well within the allowable stress envelopes. This was confirmed with dimensional surveys of specific points on the barge and jacket mudline every 15 minutes during the critical loadout phases.
The Harmony and Heritage platforms are planned by Exxon Company, U.S.A., for installation planned by Exxon Company, U.S.A., for installation offshore California, in 1200 feet (366 m) and 1075 feet (328 m) of water, respectively. The design criteria and analysis procedures are an extension of the technology used for the 850-foot (259 m) water depth Hondo platform, about ten years ago. Each of various in-place (environmental) and installation loadings are discussed, and their relative impacts on jacket weight are evaluated. Introduction Exxon Company, U.S.A.'s Hondo platform was installed in the Santa Ynez Unit in the Santa Barbara Channel in 1976. The design and construction procedures of this 850-foot (259 m) water depth platform (which are described in References 1 and 2) have evolved to meet the additional challenges presented by the Harmony and Heritage platforms, the next developments for the Santa Ynez Unit. As shown in Figure 1, the Harmony platform will be located about 3 miles (4.8 km) west of the Hondo platform, and the Heritage platform will be located about 7 (11.3 km) miles west of Harmony. Pipelines are planned to extend from Heritage to Harmony, to Hondo, to a terminal. Like Hondo, both platforms were designed by Exxon Company, U.S.A., with extensive support by its research affiliate, Exxon Production Research Company. Designs for a one-and two-piece option and for a Far East and West Coast jacket assembly are essentially complete. The anticipated schedule for the platform jacket design and construction is shown in Figure 2. To capture economies of scale, design and fabrication of the Heritage platform is planned to be simultaneous with that for Harmony, and water phase construction will be sequential. phase construction will be sequential. PHYSICAL FEATURES PHYSICAL FEATURES As shown in Figure 3, the Harmony and the Heritage platforms are similar to the Hondo platform. They are all 8-legged, pile founded platform. They are all 8-legged, pile founded structures for the support of drilling rigs, production equipment, and personnel quarters. production equipment, and personnel quarters. The size of the new platforms prohibits the use of any existing fabrication yards on the U.S. West Coast. Also, no existing barge is capable of carrying either jacket as a single unit across the Pacific. Thus, to encourage competitive bidding and launch barge development, both one-piece and two-piece (like Hondo) jackets were designed and offered to potential fabricators. potential fabricators. The deck structures on Harmony and Heritage are essentially identical. They are three-level modular decks, atop a module support frame. The deck plan is 180 feet by 145 feet (55 m by 44 m) with a total area of about 78,000 square feet (7300 m2). Two drill rigs and 60 well conductors are planned for each platform. The total topside weights above the module support frame is about 40,000 kips (mass 18,100 Mg) for each platform.
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.
customersupport@researchsolutions.com
10624 S. Eastern Ave., Ste. A-614
Henderson, NV 89052, USA
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Copyright © 2025 scite LLC. All rights reserved.
Made with 💙 for researchers
Part of the Research Solutions Family.