The Semmering Base Tunnel (SBT), with a total length of 27.3 km, is one of the leading construction projects of the Baltic-Adriatic Railway Network. The tunnel connects the two federal provinces of Lower Austria and Styria and cuts through the eastern part of the Alps. The construction lot SBT 1.1-Tunnel Gloggnitz is characterized by a complex geological- and hydro-geological architecture containing alternating competent geological structures, major fault zones, and corresponding geological transition zones. There are three main water-bearing formations at the construction lot SBT 1.1: (a) Karst-prone blocky limestone with an initial water pressure of 10 bar. The discontinuities form a highly permeable interconnected joint network with a significant storage coefficient of the groundwater table. (b) Massive to blocky dolomite with an initial water pressure of 25 bar. The systematic discontinuities and disturbed zones of subsidiary structures with karst form a permeable, interconnected joint network. (c) The transition zone of the limestone to base structure marks the most challenging area for consolidation- and sealing grouting. Weak fault rocks characterize transition zones with intense fracturing. However, as subjected to high groundwater pressure of 10 bar, these zones are associated with the potential of flowing ground conditions. Based on the overall project requirements, specific drilling- and grouting methods and materials for pre-excavation grouting have been established and successfully implemented in the construction process. The innovations include a Standpipe-Packer substituting a conventional steel standpipe, a specifically cased drilling system with grouting inserts to prevent erosion within the borehole and allow for defined grouting. In addition, this Grouting-Pipe system replaces standard tube-à-manchettes and controls the flushing while drilling with preventers. Finally, a combined cement-polyurethane grout mix (Hybrid Grout) was implemented to stabilize the grout. The implementation of these measures will be discussed in detail, and their benefits to the construction process will be highlighted.
The Semmering Base Tunnel (SBT), which has a total length of 27.3 km, is one of the most important construction projects in the Baltic‐Adriatic railway corridor. The base tunnel crosses the foothills of the Eastern Alps and connects the two federal states of Lower Austria and Styria. Due to the complex rock conditions, extensive and novel grouting systems are used. The primary target of the grouting is to reduce the permeability of the rocks and reduce the water entry (peak water ingress in the tunnelling area up to 300 l/s), as well as to improve the rock mass strength in some parts. Based on the grouting design, specific drilling and grouting procedures with various grouting materials were developed for sealing and tempering the water‐bearing areas of Grassberg and Otterstock. Innovations include the development of a standpipe packer and a cased grouting‐pipe system with grouting valves to prevent erosion along the drilling line for use in unstable borehole conditions. The combined cement/polyurethane suspension (hybrid grout) allows an extended economical use of cement suspensions.
Base tunnels usually require temporary intermediate construction accesses in order to be able to carry out the tunnelling work in a timely, economical and logistical reasonable scope. Intermediate construction accesses in the form of shafts lead to particular logistical challenges in supplying the tunnel headings. At contract SBT 1.1‐Tunnel Gloggnitz as the eastern section of the Semmering Base Tunnel, the shafts of the intermediate construction access Göstritz cannot be sunk from the surface for topographical reasons but are instead developed by an access tunnel. This fact requires the construction of complex underground structures and logistical interfaces to supply the four tunnel headings, beginning from the building site facilities, via the access tunnel, through the shafts to the tunnel face. In addition to the ongoing supply of all kinds of support measures, the excavated material is mucked by means of fully automatic belt and shaft conveyor systems. To ensure the permanent safety of the crew on‐site, the highest demands and resilience are placed on the transport systems through the two 250 m deep shafts, the ventilation and the mountain water drainage systems of up to 500 l/s. The article describes the experience and ongoing optimization of the logistics concept as well as innovative new developments that are applied in this special tunnel project.
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.
customersupport@researchsolutions.com
10624 S. Eastern Ave., Ste. A-614
Henderson, NV 89052, USA
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
Copyright © 2024 scite LLC. All rights reserved.
Made with 💙 for researchers
Part of the Research Solutions Family.