Purpose The built-transfer and operate (BOT) toll model has been a common approach for highway construction in India. Due to large amount of investment, many stakeholders and long concession period, Indian BOT toll roads become susceptible to different risks. Risk assessment is one of the essential and difficult steps of risk management that enables professionals to quantify and analyze the risks that may hamper the BOT toll project performance in terms of cost, quality, safety and time. The purpose of this study is to identify and assess the risk factors by the fuzzy probabilistic model.
Design/methodology/approach The comprehensive literature review has been carried out for identification of Indian BOT toll roads projects' risk factors. A structured questionnaire was prepared which was then filled by contractors, government officers, academicians, project managers and consultants. For risk assessment, a systematic quantitative-based fuzzy probabilistic model is proposed with the help of lab-view, as a risk assessment technique to simulate the impreciseness of human judgment and to improve the assessment accuracy.
Findings The risk assessment is one of the difficult tasks because BOT toll roads have complex structure. In this study, total 71 risks have been identified and categorized under 14 risk factors on a basis of case studies of Indian toll roads and literature review. All risks have been assessed by the fuzzy probabilistic model by lab-view. The land acquisition is the most crucial risk of BOT toll roads project which is subsequently followed by construction time and cost over-run. Also, Indian BOT toll roads are facing the traffic shortfalls critically, which became a reason toward declination trend for investment in BOT toll projects by the private players. Other risks like political risks, contractual and social risk badly are affecting the project performance. Early risk identification and assessment can be beneficial for the project, which is required to prepare the risk response strategy before the project commencement.
Originality/value This study throws light on comprehensive risk assessment and framework modeling of the risk assessment for the BOT toll roads project in India. This comprehensive risk assessor model can be used for BOT toll roads in Indian scenario for prioritization of the critical risk. It is important for the public and private sectors to establish an effective risk assessor model for public–private partnership (PPP) projects to achieve win-win condition for both.
IJCAT addresses issues of computer applications, information and communication systems, software engineering and management, CAD/CAM/CAE, numerical analysis and simulations, finite element methods and analyses, robotics, computer applications in multimedia and new technologies, computer aided learning and training. Contents: IJCAT is a refereed, international journal, published quarterly, providing an international forum and an authoritative source of information in the field of Computer Applications and related Information Technology.
scite is a Brooklyn-based organization that helps researchers better discover and understand research articles through Smart Citations–citations that display the context of the citation and describe whether the article provides supporting or contrasting evidence. scite is used by students and researchers from around the world and is funded in part by the National Science Foundation and the National Institute on Drug Abuse of the National Institutes of Health.