Applied energy and mass balance optimization re-engineering: case on Industri Gula Glenmore, Ltd.

Abstract: The Glenmore Sugar Industry, Ltd. is designed for 8000 TCD production or 273 TPH. The process required approximately 136 TPH based on the Steam on Cane (SoC) 50%. As the factory's primary input, Sugar Cane cannot supply 8000 TCD Factory Capacity, so 6000 TCD is chosen as an alternative. After commissioning, a lack of steam for servicing the process occurred because the Turbine at full load required 7,6 Kg/kWh. Desuperheater supports the additional steam for the process, which is only 20 TPH. Meanwhile, the ste… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...

Citation Types

0
0
0

Publication Types

Select...

Relationship

0
0

Authors

Journals

citations
Cited by 0 publications
references
References 9 publications
0
0
0
Order By: Relevance

No citations

Set email alert for when this publication receives citations?