Automated Computer Vision-Based Construction Progress Monitoring: A Systematic Review

Abstract: The progress monitoring (PM) of construction projects is an essential aspect of project control that enables the stakeholders to make timely decisions to ensure successful project delivery, but ongoing practices are largely manual and document-centric. However, the integration of technologically advanced tools into construction practices has shown the potential to automate construction PM (CPM) using real-time data collection, analysis, and visualization for effective and timely decision making. In this study,… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
5

Citation Types

0
18
0

Year Published

2023
2023
2024
2024

Publication Types

Select...
4
2

Relationship

1
5

Authors

Journals

citations
Cited by 24 publications
(18 citation statements)
references
References 138 publications
0
18
0
Order By: Relevance
“…This plan is used to guide the project team in the execution of the project and to track progress over time. The project manager is responsible for overseeing the project plan and making any necessary adjustments to ensure that the project stays on track and within budget (Sami Ur Rehman et al ., 2022a, b). To complete the construction project on time, achieve expected time-related goals and stay aware of the status of the project at any given time, construction project management teams conduct continuous worksite inspections throughout the lifecycle of the project; usually termed as ‘construction progress monitoring’ or ‘construction progress tracking’ (Mantel and Meredith, 2009).…”
Section: Introductionmentioning
confidence: 99%
See 4 more Smart Citations
“…This plan is used to guide the project team in the execution of the project and to track progress over time. The project manager is responsible for overseeing the project plan and making any necessary adjustments to ensure that the project stays on track and within budget (Sami Ur Rehman et al ., 2022a, b). To complete the construction project on time, achieve expected time-related goals and stay aware of the status of the project at any given time, construction project management teams conduct continuous worksite inspections throughout the lifecycle of the project; usually termed as ‘construction progress monitoring’ or ‘construction progress tracking’ (Mantel and Meredith, 2009).…”
Section: Introductionmentioning
confidence: 99%
“…Project monitoring and control are responsible for safeguarding the project from any delays, cost overrun. CPM typically involves regular inspections of the construction site and the use of tools such as Gantt charts, project management software and progress reports to track progress and identify areas for improvement (Sami Ur Rehman and Shafiq, 2022).…”
Section: Introductionmentioning
confidence: 99%
See 3 more Smart Citations