2013
DOI: 10.3390/buildings3030506
|View full text |Cite
|
Sign up to set email alerts
|

Construction Delay Analysis Techniques—A Review of Application Issues and Improvement Needs

Abstract: The time for performance of a project is usually of the essence to the employer and the contractor. This has made it quite imperative for contracting parties to analyse project delays for purposes of making right decisions on potential time and/or cost compensation claims. Over the years, existing delay analysis techniques (DATs) for aiding this decision-making have been helpful but have not succeeded in curbing the high incidence of disputes associated with delay claims resolutions. A major source of the disp… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

1
53
0

Year Published

2014
2014
2024
2024

Publication Types

Select...
6
4

Relationship

0
10

Authors

Journals

citations
Cited by 65 publications
(54 citation statements)
references
References 20 publications
1
53
0
Order By: Relevance
“…The reliability of the delay analysis results is validated by resource-loaded and levelled baseline programmes, these programmes provide reliable task duration, network logic, and realistic float values in non-critical activities as earlier researchers have done. While this case study uses a hypothetical project, the proposed claims scenarios largely reflect that of a typical construction delay claims settings, both in relevance and context and supports few investigation [13]. This study gets its strength, by conducting similar study being undertaken in future based on real life project data to validate the case study.…”
Section: A the S-curvementioning
confidence: 80%
“…The reliability of the delay analysis results is validated by resource-loaded and levelled baseline programmes, these programmes provide reliable task duration, network logic, and realistic float values in non-critical activities as earlier researchers have done. While this case study uses a hypothetical project, the proposed claims scenarios largely reflect that of a typical construction delay claims settings, both in relevance and context and supports few investigation [13]. This study gets its strength, by conducting similar study being undertaken in future based on real life project data to validate the case study.…”
Section: A the S-curvementioning
confidence: 80%
“…(Hudon, 2015). These techniques are, however, rarely available within project management systems besides ignoring the resource constraints and the interdependencies between the causes of delays and the delays themselves (Braimah, 2013). The application of these methods also requires detailed records in order to establish the costs of the different activities of the work packages, especially the activities affected by the problem from the very beginning of the project (Nelson, 2011).…”
Section: Analysis Of the Impacts Resulting From The Problems Detectedmentioning
confidence: 99%
“…[1] The Malmaison's Approach suggests that when concurrent delay occurs, one an owner risk event and the other a contractor risk event, only one of the delays is the dominant cause for the delay to the project and prevails over the other cause of delay. [2]. Such approach is described by the Editor of Keating as "the now excepted approach in resolving concurrency in the context of extension of time claims" [5] Another factor to consider is that total float values used to measure delays are a product of programme logic.…”
Section: B the Incomprehensibility Of The Current Delay Methodsmentioning
confidence: 99%