2000 Power Engineering Society Summer Meeting (Cat. No.00CH37134)
DOI: 10.1109/pess.2000.867539
|View full text |Cite
|
Sign up to set email alerts
|

Development of an interactive rule-based system for bulk power system restoration

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
6
0

Publication Types

Select...
2
1

Relationship

0
3

Authors

Journals

citations
Cited by 3 publications
(6 citation statements)
references
References 0 publications
0
6
0
Order By: Relevance
“…During reconfiguration process, since the restored system is under a light‐load condition, excessive reactive power produced by the transmission lines could result in some operational problems, such as steady‐state overvoltage and stator end overheating etc. Thus, minimisation of charging reactive power should be the primary objective of energising path optimisation [27]. Under such circumstances, the path optimisation problem could be modelled as a local minimum spanning tree problem (also called the Steiner tree problem) in graph theory [13, 28, 29].…”
Section: Analysis Of Alternative Energising Path Optimisation Problemmentioning
confidence: 99%
See 1 more Smart Citation
“…During reconfiguration process, since the restored system is under a light‐load condition, excessive reactive power produced by the transmission lines could result in some operational problems, such as steady‐state overvoltage and stator end overheating etc. Thus, minimisation of charging reactive power should be the primary objective of energising path optimisation [27]. Under such circumstances, the path optimisation problem could be modelled as a local minimum spanning tree problem (also called the Steiner tree problem) in graph theory [13, 28, 29].…”
Section: Analysis Of Alternative Energising Path Optimisation Problemmentioning
confidence: 99%
“…(ii) Reactive power constraint: The excessive charging reactive power generated by transmission lines may lead to sustained overvoltage since the system is in a light-load state [27]. Therefore, the reactive power constraint [30] is defined as follows:…”
Section: Constraintsmentioning
confidence: 99%
“…To minimize the duration, an optimal power flow (OPF) algorithm with minimal adjustment of each generating unit is established. Based on the ramping rate of a generating unit, the minimal adjustment corresponds to the shortest time to implement this objective: In this problem, (10) is the limit of each generating unit, and it is determined by the upper limit and ramping rate of a generating unit; (11) represents power flow equations for the energized block at stage ; (12) describes physical constraints of each generating unit, critical load, and dispatchable loads; (13) and (14) are limits of voltage and power flow through each line at stage . It should be noted that all constraints at stage are already met in the last step; only the constraints for stage are involved here.…”
Section: Algorithm 3: Finding An Acceptable Operating Point Of the Symentioning
confidence: 99%
“…Restoration plans are developed with basic simulation tools for power flow, dynamics [3], [9], [10], and electromagnetic transients [11], [12]. These plans developed offline are used as guidelines for dispatchers in an online environment [13], [14]. Dispatchers need to adapt to actual outage scenarios and available resources and be able to develop the strategy based on their experience.…”
mentioning
confidence: 99%
“…Hao is with the School of Electrical Engineering and Control Science, Nanjing Tech University, Nanjing, China (e-mail: haolili@njtech.edu.cn). DOI: 10.35833/MPCE.2021.000030 power outage scenarios, external environments, and restoration processes, in addition to evaluating the expected restoration incomes and security risks of restoration plans in the decision-making process [26], [32], some studies propose the on-line decision-making frameworks to monitor the operation results of restoration plans and trigger the re-optimization process when necessary [26], [33], [34], but there is still a lack of adaptive strategies to deal with uncertain events in multi-partitions. Besides, there is little research on collaborative restoration with distribution systems.…”
Section: Introductionmentioning
confidence: 99%