Interface Problems in Change Order-Challenged Projects

Abstract: Change orders are among the main sources of problems challenging timely completion of construction projects. The significantly needed conducive interaction among project participants to mitigate completion delay risk due to change orders is often hampered by interface problems. This article describes potential sources of interface problems and their role in affecting completion time of change order-challenged infrastructure construction projects in Indonesia. The identified sources then serve as inputs to form… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1
1
1

Citation Types

0
6
0
1

Year Published

2019
2019
2024
2024

Publication Types

Select...
5
1

Relationship

0
6

Authors

Journals

citations
Cited by 6 publications
(7 citation statements)
references
References 22 publications
0
6
0
1
Order By: Relevance
“…Table 2 lists the projects and respondents involved in the questionnaire survey. A part of the survey's result (from five among the 11 projects) was already described in a previous article (Marzuki, Oktavianus and Regina, 2018). For the present article, the numbers of respondents are increased and the types of infrastructure constructed are more varied to obtain a more complete representation of Indonesian infrastructure construction projects.…”
Section: Methodsmentioning
confidence: 91%
See 2 more Smart Citations
“…Table 2 lists the projects and respondents involved in the questionnaire survey. A part of the survey's result (from five among the 11 projects) was already described in a previous article (Marzuki, Oktavianus and Regina, 2018). For the present article, the numbers of respondents are increased and the types of infrastructure constructed are more varied to obtain a more complete representation of Indonesian infrastructure construction projects.…”
Section: Methodsmentioning
confidence: 91%
“…Meanwhile, Chen, Reichard and Beliveau (2008) identify comprehensive cause factors of interface problems from six interrelated perspectives: people/participants, methods, processes, resources, documentation, project management and environment. Marzuki, Oktavianus and Regina (2018) conducted a research on interface problems in Indonesian infrastructure construction projects mainly based on cause factors categorisation proposed by Al-Hammad (2000) and Chen, Reichard and Beliveau (2008).…”
Section: Literature Reviewmentioning
confidence: 99%
See 1 more Smart Citation
“…The second highest factor in-group score was the factor “differing site conditions” which had a score of 0.668. This factor was ranked second in the study from Senouci et al (2017) in Qatar; ranked sixth in the study from Muhammad et al (2015) in Nigeria; and identified as one of the key causes in the study from Hansen et al (2020) in Indonesia; and the most common cause of change orders in construction projects in Indonesia according to Marzuki et al (2019). While taking into consideration the group score, it comes in tenth place.…”
Section: Discussionmentioning
confidence: 98%
“…define change order as "modifications or alterations to pre-existing conditions, assumptions, or requirements". Change orders (also known as variation orders) are common in construction (Shrestha & Fathi, 2019;Kermanshachi et al, 2018;Shrestha & Maharjan, 2018;Marzuki et al, 2019;Du et al, 2016;Alleman et al, 2020;Khanzadi et al, 2018). Change order is inevitable aspect of construction industry and also one of the important factors in the failure of projects (Keane et al, 2010;Kermanshachi et al, 2020).…”
Section: Introductionmentioning
confidence: 99%