“…Figure 10 demonstrates that in the event that the delivery of the prefabricated components required in activity 9 is delayed by 2 days, the maximum completion time of the project is delayed by 24 days. Activities 10,11,12,13,20,21,22,23, and 24 all delayed the start time compared with the schedule in Figure 8. Especially for activity 20, even if all its predecessors have been executed on the 13th day, due to the constraints of renewable resources, activity 20 has to wait until the 16th day to start work.…”