Solution methods for the design and construction of contract KAT3 of the Koralm Tunnel /

Abstract: The very variable geological conditions require two completely independent machine concepts for contract KAT3 of the Koralm Tunnel, which have been taken into account with the planned use of a shield machine capable of being rebuilt. This article discusses the essential constructional requirements for machinery and construction methods based on the current state of design and knowledge. Koralm Tunnel overviewThe most important structure along the new high-speed railway line between Graz and Klagenfurt is the K… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1

Citation Types

0
1
0
1

Year Published

2011
2011
2024
2024

Publication Types

Select...
3

Relationship

1
2

Authors

Journals

citations
Cited by 3 publications
(2 citation statements)
references
References 1 publication
0
1
0
1
Order By: Relevance
“…Therefore, a shield machine with earth pressure components was favoured as a solution (SM-V5). In the area of the tertiary sediments, this machine offers the possibility of working -depending on the geological and geotechnical conditions -in different operating modes ("open", "transition" and "closed" modes) to ensure safe face conditions at all times [3]. The machine is to be converted to a TBM with shield for the crystalline bedrock section.…”
Section: Adaptation Of the Machine Type To The Geological/ Geotechnicmentioning
confidence: 99%
See 1 more Smart Citation
“…Therefore, a shield machine with earth pressure components was favoured as a solution (SM-V5). In the area of the tertiary sediments, this machine offers the possibility of working -depending on the geological and geotechnical conditions -in different operating modes ("open", "transition" and "closed" modes) to ensure safe face conditions at all times [3]. The machine is to be converted to a TBM with shield for the crystalline bedrock section.…”
Section: Adaptation Of the Machine Type To The Geological/ Geotechnicmentioning
confidence: 99%
“…Als Vorzugslösung wurde daher eine Schildmaschine mit Erddruckkomponenten favorisiert (SM-V5). Diese Maschine bietet im Bereich der tertiären Sedimente die Möglichkeit, je nach geologisch-geotechnischen Randbedingungen in unterschiedlichen Betriebsmodi ("open"-, "transition"-und "closed mode") zu agieren, um zu jedem Zeitpunkt sichere Ortsbrustverhältnisse gewährleisten zu können [3]. Für den kristallinen Festgesteinsabschnitt erfolgt ein Umbau zur TBM-S.…”
Section: Tunnelling Class Vk 1 (Open Mode With Provision Of Compresseunclassified