The Results of Dynamic (Pile Driving Analysis) and Traditional Static Piling Tests in Capital of Kazakhstan

Abstract: Traditionally, pile load tests in Kazakhstan are carried out using static and dynamic load test methods. Static pile load test is the most reliable method to obtain the load-settlement relation of piles. Most of the static pile load tests are performed using reaction systems. Furthermore, cost and time for the static pile load test are relatively high compared to the dynamic pile load testing. Therefore, the number of pile load tests in construction site is limited to 2 or 5 piles in usual of constructed piles… Show more

Help me understand this report

Search citation statements

Order By: Relevance

Paper Sections

Select...
1
1

Citation Types

0
3
0

Year Published

2017
2017
2024
2024

Publication Types

Select...
5
1

Relationship

1
5

Authors

Journals

citations
Cited by 6 publications
(3 citation statements)
references
References 2 publications
0
3
0
Order By: Relevance
“…Standard -SNiP RK 5.01-03-2002 -ultimate value of settlement of the tested pile is determined as and depending on the category of construction is equal to 16 or 24 mm. The last argument shows the conditional character of SLT method [3][4][5][6][7].…”
Section: Fig 2 Field Pile Test By Scplt Methodsmentioning
confidence: 99%
See 2 more Smart Citations
“…Standard -SNiP RK 5.01-03-2002 -ultimate value of settlement of the tested pile is determined as and depending on the category of construction is equal to 16 or 24 mm. The last argument shows the conditional character of SLT method [3][4][5][6][7].…”
Section: Fig 2 Field Pile Test By Scplt Methodsmentioning
confidence: 99%
“…In modern CFA technology, the systematic employment of devices auto-recording the drilling data represent a real breakthrough considering that in the past the CFA method was not accurate, and relied on the operator's ability: now such devices guarantee the control and recording of the data during the whole construction process. The recorded working data are usually drilling/withdrawal speed, rotation speed, depth, concrete pressure and delivery rate per increment of auger lift during casting [4][5]. The CFA construction sequence is comprised of five stages in Figure 1.…”
Section: The Pile Installation Through Technology Cfamentioning
confidence: 99%
See 1 more Smart Citation