The Tulfes Pfons H33 construction contract of the Brenner Base Tunnel includes a 15 km long exploratory tunnel. The tunnel is being driven by an open gripper TBM, permitting a view of the surface of the rock mass, to achieve the best possible geological and geotechnical exploration for the deep tunnel system. Geologists and geotechnical engineers follow the TBM excavation on a daily basis and guarantee ongoing mapping and interpretation of the rock mass classification and of the TBM data. All data from the exploratory tunnel advance, the TBM data, the measured deformations and the seismic explorations as well as the findings of geological mapping are incorporated into the geotechnical longitudinal section, which serves as the basis for the tenders of the main construction contracts. In particular, discussions take place with the designer of the following contract, how the encountered fault zones and overbreaks can be passed successfully in the main tunnels. Both the improvement of the rock mass from the exploratory tunnel and ramps are considered in order to excavate the most difficult fault zones from the exploratory tunnel.