Penjadwalan Pekerjaan Proyek Struktur Atas Dengan Menggunakan Repetitive Scheduling Method

Abstract: Growth in the construction sector will have a very positive impact on economic growth both directly and indirectly. For this reason, it is necessary to have a good and efficient time control management. In this research, rescheduling will be conducted using the Repetitive Scheduling Method. From the rescheduling results, it was found that scheduling the project could be completed in a much faster time frame. It takes 5 weeks from the 10 weeks schedule plan.