Purpose
Project complexity (PC) governs project success, but the project management literature primarily focuses on performance measures and rarely examines the complexity factors, especially for megaprojects. This paper aims to determine the most significant complexity factors for the railway megaprojects in India.
Design/methodology/approach
A mixed approach using the Delphi and best–worst method (BWM) helped to identify, validate and determine the most critical factors that require intervention to diminish variance from project performance.
Findings
The BWM resulted in stakeholder management, followed by organizational and technological complexity as significant complexity factors, and the varied interests of the stakeholder as the most important among the 40 subfactors.
Practical implications
The finding indicates the necessity for strategic, tactical and operational-level interventions to effectively manage the complexity affecting project efficiency because of the varied stakeholders. This paper will guide the project and general managers to prioritize their resources to handle complexity for effective project performance measured in terms of time, cost and quality and help them make strategic decisions. The research findings of this study are expected to help researchers and practitioners in better planning and smoother execution of projects. In addition, this study would help the researchers formulate policies and strategies for better handling of the projects.
Originality/value
This study adds significant value to the body of knowledge related to PC in megaprojects in developing countries. The result of the investigation underlined that nine complexity factors and seven unique subfactors, namely, the sustainable environment, timely availability of information, communication in both directions, interdepartmental dependency and coordination, design, statutory norms, site challenges, socioeconomic conditions, the tendency of staff to accept new technology and the frequent changes in the requirements of stakeholders are significant in railway megaprojects. The BWM is applied to rank the complexity factors and subfactors in the case area.